Montana Department of Revenue Logo

Liquor Warehouse Expansion Project

Did you know the Department of Revenue’s Alcoholic Beverage Control Division is in the process of expanding its liquor warehouse?

Liquor Warehouse Expansion Project Image

 

It’s true! During the 2021 and 2023 Montana Legislative Sessions, the department was fortunate to receive funding to start an expansion project.

The warehouse is located in Helena and is the hub where all liquor products are shipped before being sold throughout the state of Montana. More than 1 million cases of liquor are shipped from the warehouse each year to 95 privately owned agency liquor stores located throughout the state of Montana.

The current facility was built in the late 1970s, specifically for the department’s liquor operations. However, liquor sales have continuously increased each year, creating the need for additional space.

The department has been working with CWG Architecture for several months on the design and the project has been awarded to a contractor.

The expansion project will include a 30,000-square-foot addition to the south side of the current facility (depicted in the darker brown color in the picture).

The addition will be twice as tall as the current facility and equipped with an automated storage and retrieval system.

Pallets of liquor will be placed on a conveyor system. The automated storage and retrieval system will have two cranes that will take the pallets of liquor and automatically store and recall products as needed.

By using an automated storage and retrieval system it will allow the department to store a greater number of pallets of liquor than it could with other racking systems.

The project is estimated to be completed by April 2025.

Check back periodically for additional updates and progress.

 

January 2025

With the exterior of the new addition largely completed, the construction crew has focused much of the last two months working on the interior.

Many years ago, the department received alcoholic beverages via train cars.  A large door in the southeast corner of the building would open and the train cars would enter the building on a set of tracks.  That large doorway was reopened by the construction crew and will be one of the two forklift doorways used to get pallets of liquor to and from the existing facility into the addition.

Southest Passage of ABCD Liquor Warehouse
A second opening was cut into the existing south exterior wall to allow for additional forklift use.
Preparation to cut the warehouse wall
A construction worker in a scissor lift working on the wall cut preparation.
A construction worker in a safety vest and hard hat stands on a blue Genie scissor lift inside an industrial warehouse, working on a large concrete wall with three vertical openings. Stacks of wooden pallets are piled nearby, and construction materials are visible in the background.
A wide view of the liquor warehouse construction site, showing workers on a scaffold working on the masonry wall.

The first container of parts for the automated storage and retrieval system has arrived too.  The picture below shows just a portion of the first container.  Several more will be coming over the coming weeks.

Pallets in a row containing parts for the automated storage and retrieval system.

Past Updates

Except for installing all the doors, the outer shell of the addition is largely completed.  Over the next several months, much of the work will happen inside the structure.

View of new addition to liquor warehouseCorner of addition to liquor warehouseView of addition beside loading area
The month of October was a busy one with lots happening on the job site.  During early October, the second half of the concrete slab was poured in the new addition. Mid to late October, the concrete was poured for the curbing in the parking, a large portion of the asphalt was removed and resurfaced, a sidewalk was partially installed along Airport Road, and the wall panels continued to go up.
Warehouse construction site, with warehouse metal framing exposed.
Inside view of the warehouse under construction, with steel beams and open framework.
A newly poured concrete sidewalk along the road
Groung being prepared at a loading dock area at the warehouse
View of liquor warehouse construction site
Freshly paved asphalt in a parking lot, with yellow-painted parking lines and newly installed curbs.
Curbed island with orange construction cones around it in a parking lot
A wide view of a parking lot preparation site, with dirt piles and construction vehicles.
Construction site with trucks parked along the warehouse.
A large construction vehicle removing asphalt
A newly constructed curbed island with orange posts in the center
The construction crew continued its progress on the roof during the month of September and will continue into October. During the latter part of September, the construction crew started to hang the wall panels, prepped the parking lot for curbing, and poured the first half of the concrete floor.
First half of slab poured
Curbing preparation work
Additional view of curbing preparation
Concrete work in progress
Concrete pour
Concrete pour with pump truck
Parking lot preparation
Exterior walls construction
Another view of exterior walls
Most of the noticeable work happened 60 plus feet up in the air for the month of August.  The metal decking was installed, and the crew started to lay down much of the roofing material.
A close-up view of a large steel frame structure with metal decking installed on the roof level.
 A side view of a large, elevated steel structure at the warehouse under construction.
A view of a rooftop with stacks of white roofing insulation material placed on top of corrugated metal decking.
Showing roofing reworking being done
The warm month of July didn’t slow progress down at the liquor warehouse job site.  The south masonry wall closest to the existing building was completed.  Additionally, several trucks of steel arrived, and the construction crew made quick work erecting the structure.
A crane lifts steel beams into place for the warehouse extension, while workers prepare the site below.
Steel beams and columns are being positioned for the warehouse expansion.
The steel skeleton of the warehouse extension progresses, with construction activity on the ground.
Steel framework of the liquor warehouse expansion rising tall next to the existing building.
The steel framework of the Montana Department of Revenue's liquor warehouse expansion project is nearly complete, with beams and columns in place and construction equipment visible on site.
A crane assists in erecting the steel structure of the liquor warehouse expansion
Progress continues to be made on the liquor warehouse expansion project.  Work on the footings and foundation walls continued and the first masonry wall along the southern wall of the existing building started to go up quickly.
The construction site viewed from above showing the foundation being laid out.
An overview of the construction site showing a foundation being prepared.
Construction workers are on a raised scaffold working on the masonry wall of the liquor warehouse.
A wide view of the liquor warehouse construction site, showing workers on a scaffold working on the masonry wall.

The installation of several storm water tanks took place in the center of the truck circulation area.  Despite the work, incoming and outgoing trucks were able successfully navigate the area with little to no impact.  Below is a picture of the area being excavated, temporary pilings going in, the storm water tanks being installed, and recovering the area with dirt.

On the southside of the property, work continues on the footings and the start of the foundation walls.

A panoramic view of the liquor warehouse construction site showing a large dirt excavation area with multiple construction vehicles and equipment against a cloudy sky. Semi-trucks and trailers are parked in the distance.
Close-up of a construction worker wearing an orange vest and helmet, working next to a large excavation pit with a heavy drill machine inserting a piling into the ground. Construction barriers and equipment are visible around the site.
Overcast sky above a construction site with two large excavators digging in a fenced-off area filled with dirt, construction materials, and yellow corrugated pipes laid on the ground.
Elevated view of the liquor warehouse construction site featuring heavy machinery, including a bulldozer and an excavator working around a large, deep excavation with protective barriers and construction workers visible.
Aerial view of the liquor warehouse construction site with multiple areas of excavation and construction machinery. The area is surrounded by industrial buildings under a clear sky.
A long trench reinforced with wooden and steel beam footings with scattered construction materials and machinery, lined with the beginnings of the foundation walls.

Lots of work continues at the state liquor warehouse on its expansion project with the footings of the new building being the most noticeable.

In preparation for the installation of several large storm water tanks in the receiving area of the state liquor warehouse, the construction crew is building a temporary semi-truck approach on the property immediately to the west to enable the operations of the liquor warehouse to continue. Without this approach, semi-trucks would be unable to back up to our receiving doors.

Early morning construction site preparation
Concrete work with a red pump truck
Construction workers managing a concrete pump
Concrete being poured into trench foundations
View of concrete foundation work
Detailed shot of concrete footings installation
Semi-approach construction site
View of construction machinary

On-site work has officially commenced on the liquor warehouse expansion project. The first stage involves rerouting a sewer pipe that crosses the job site. This work is estimated to take a few weeks.

Below are a few pictures of this portion of the project.

Liquor Warehouse construction site during winter of 2024. Large green pipes rest beside the snow in front of a yellow excavator.
A construction worker wearing a high-visibility vest stands between two large excavators on the liquor warehouse worksite.
Liquor Warehouse Construction Site marked by orange traffic cones with two large excavators in the background.